排水通气帽应高出屋面(超齐全给排水施工工艺标准做法照片,参考性强)
1、按实际梁弧度下料,并采用挠性卡箍连接,保证管道与梁的弧度一致
![](https://img.cha138.com/20230527/3ec9b113e30e430f8d587e2adea3262d.jpg)
2、 挖眼下料准确,焊缝均匀饱满
![](https://img.cha138.com/20230527/87dccd3705344f7d8ffa11f8e8c86709.jpg)
3、穿墙、穿顶板
![](https://img.cha138.com/20230527/f337ff6a01ed454f81cd63f5c68554b7.jpg)
穿墙管道保护
![](https://img.cha138.com/20230527/d9eba5ab190f4340838ac77370792c27.jpg)
4、立管止水台
![](https://img.cha138.com/20230527/be2eb50fb17746db8735567a47542643.jpg)
5、接水斗
![](https://img.cha138.com/20230527/bba5dbac429a4fe0bb7202c09948427a.jpg)
![](https://img.cha138.com/20230527/edd8ed481dff4a3c9ba1da71f6f52616.jpg)
![](https://img.cha138.com/20230527/74cfe12c2fff4c8ab46911e3840e4bfb.jpg)
6、屋面管道
![](https://img.cha138.com/20230527/750b8564df68497c830625d85b52ea8d.jpg)
![](https://img.cha138.com/20230527/d70a8349ace94fc994866ccd9dda773d.jpg)
![](https://img.cha138.com/20230527/24b8168f4b0348c4bec7aeab0d2f2b07.jpg)
![](https://img.cha138.com/20230527/8939abce5cb644278aa44e31ac0c22d7.jpg)
7、通气帽
![](https://img.cha138.com/20230527/993481fcb7f04b1b8e85de772db77ce1.jpg)
![](https://img.cha138.com/20230527/d6d9c5b2c6fd402a8fe79738900f3345.jpg)
注:上人屋面透气管不小于2.0米。
8、结合土建装饰处理,板底或墙面用管道装饰圈遮盖,整体效果清爽美观
![](https://img.cha138.com/20230527/9bdb76c2a1924138a77949d6088f6839.jpg)
9、跨越管道处做过桥处理
![](https://img.cha138.com/20230527/69afcff6f86e45b8978db964538ffee0.jpg)
10、水表安装在一层采光井内,给水支管顺着外墙垂直敷设。水表、表前阀、表后阀安装位置竖直一条线,管道支架成“八”字形安装,给水支管间间距均匀 。
![](https://img.cha138.com/20230527/a37bc981aa594d2b89af8e4a31866a46.jpg)
11、精美的给水设备间
地面处理与设备互相辉映,整洁大方表识美观
![](https://img.cha138.com/20230527/d01e940d04384ca2b7d53b03ea47f824.jpg)
![](https://img.cha138.com/20230527/807d9d8c6e124cb7a88bce1e1ae6254c.jpg)
12、消防泵房
a、接地跨接:设备、伸缩节、电源线
b、滴水弯、金属卡普利管不超0.8米
c、减震措施:出水管弯头、设备
d、金属软管不能做持续导体
![](https://img.cha138.com/20230527/351de48d08e74a288e58a691d290c461.jpg)
![](https://img.cha138.com/20230527/abf9c0d2e7b84468ba0932674822a47a.jpg)
1、设备及支架防腐台 2、螺栓上油戴塑帽3、排水沟及警示带 4、标识清楚5、高度朝向一致6、油漆鲜艳,分色明确
![](https://img.cha138.com/20230527/0b30b4e8e2854bca986a79102d1ab052.jpg)
![](https://img.cha138.com/20230527/0b14ef5ac8e64f06934d4e4a4e2e73dd.jpg)
报警阀组
1)距地面高度宜为1.2米,两侧距墙不小于0.5米,正面距墙不小于1.2米;
2)每个湿式报警阀与预做用阀控制的喷头数量不宜超过800个;
3)报警阀处的地面应有相应的排水设施;
4)供水总控制阀应处于开启状态,并采用信号碟阀;当不采用信号阀时,应设锁定阀位的锁具;
5)因雨淋阀组背面需接管,中心与背面墙距离不小于250㎜。
![](https://img.cha138.com/20230527/c091bda5dc0c48239337b61f6dd42cf5.jpg)
![](https://img.cha138.com/20230527/f8f9fa042f8e4fa081b221209d76d7ff.jpg)
设备接地要有专门的端子压接,不能用设备螺栓
![](https://img.cha138.com/20230527/7738ad7e4942404d9047c88d00c32580.jpg)
![](https://img.cha138.com/20230527/7a8018f4852142c59febb3f021a792b5.jpg)
设备机房的接地
![](https://img.cha138.com/20230527/dccee12333ed44af8269c5ea54df8aae.jpg)
![](https://img.cha138.com/20230527/1a0d82d4d27e483b9da3dd373794d3e5.jpg)
设备及管道的排列
![](https://img.cha138.com/20230527/0e86e172f7cd4aa4af42abecf4a5328f.jpg)
![](https://img.cha138.com/20230527/3731a30c9b9b4ddca38afc586903e3fc.jpg)
设备四周警示带的做法
消防泵房内应有值班室
![](https://img.cha138.com/20230527/e3a1028fcb2145a6b63907544bcc9a66.jpg)
![](https://img.cha138.com/20230527/db0d9239727f4972a4b0aad18fd85d81.jpg)
把警铃从设备间引进值班室
![](https://img.cha138.com/20230527/5c7f8dc03eba44c7bb64d39771ee6352.jpg)
![](https://img.cha138.com/20230527/c575216ac2b94e7fb5cd748425cac31a.jpg)
把警铃从设备间引进值班室设备及动载管道的减震:固定规范、合理,与基础正确的连接,稳定性好,对有减振要求的设备,减振的设备稳定可靠,接管、补偿都达到工艺要求 。
![](https://img.cha138.com/20230527/79d38f918efc4fe68f0e4dc448819996.jpg)
接地、标识及底部处理
![](https://img.cha138.com/20230527/729570dfe971430a9d84ff1290007cf6.jpg)
13、某大厅远程30米射流球形喷口安装
![](https://img.cha138.com/20230527/6c187802774b4e79a39d174401c0777c.jpg)
来源:网络
如有侵权,请联系删除
相关参考
一、屋面上设备安装1)屋面设备无破损污染,涂层均匀包括支架、托架。2)风机支座与基础接触紧密,平正牢固,基础中心线与风机中心线垂直,减震装置齐全有效并有防松动措施。3)进出风口应有安全防护装置,法兰连接严...
一、屋面上设备安装1)屋面设备无破损污染,涂层均匀包括支架、托架。2)风机支座与基础接触紧密,平正牢固,基础中心线与风机中心线垂直,减震装置齐全有效并有防松动措施。3)进出风口应有安全防护装置,法兰连接严...
方管图纸标注(结构工程施工工艺标准做法24条,创优图集请收好)
...。垫层坡向集水坑。因条件受限无法设置的,应采取其他排水措施,保证不积水。2、地下室车道两侧剪力墙、楼(电)梯间四周剪力墙、高出地下室顶板的剪力墙根部,女儿墙、屋面楼梯间墙体、设备间墙体、公共建筑的公共...
水泥排水管可以说是保证排水系统安全和功能的重要配件之一。所以在住宅处水泥排水管的设置会直接受影响居民生活的质量,因而对于水泥排水管的设置需谨慎进行。接下来佛山水泥管详细地为大家介绍:住宅较多是将排水管...
...计★质量要点1)屋面施工前须进行深化优化,主要包含排水坡度、坡向,分格缝位置,透气管、排气管位置,烟道、防水收头、出屋面门口、圆弧泛水等细部节点做法。2)深化设计时,对于大屋面优先选用设置天沟单坡排水方...
末端喷淋(建筑给排水工程屋面、屋顶水箱间、楼层工序控制要点)
#1屋面1.1透气管实体图例构造做法图工艺控制要点:1、透气管应高度一致,成排成线;透气管底部设置止水台,止水台高度高于装饰面250mm,并不低于当地积雪深度;2、出屋面透气管宜采用整根管道,透气管顶端需装有通气帽;...
虹吸式雨水排水系统施工工艺标准1.适用范围和编制依据1.1适用范围本工艺标准适用于建筑给、排水工程中的虹吸式雨水排水系统安装工程。1.2编制依据《建筑建筑给水、排水及采暖工程施工质量验收规范》GB50242-2002《虹吸式...
一、工程概况京台线建瓯至闽侯高速公路福州段牛岩山隧道,左线全长9252米,右线全长9198米,隧道设计行车速度:80km/h,最大埋深约500米。隧道左线采用三区段斜竖井送排式分段纵向通风,左线斜井水平距长度1366.66m,纵坡14.56...
一、管材建筑排水内螺旋管道包括塑料内螺旋管和钢塑复合加强型内螺旋管。塑料内螺旋管分为硬聚氯乙烯普通型内螺旋管和硬聚乙烯、高密度聚乙烯或聚丙烯塑料加强型内螺旋管。钢塑复合加强型内螺旋管采用铸铁管件,铸铁...